ClarkTE

Acceptance Testing

Verify New Equipment Performance Before It Enters Service

Why Acceptance Testing Matters

Industry data shows 15-30% of new electrical equipment has defects or deviations from specifications at delivery. Without proper acceptance testing, these issues remain hidden until equipment fails under load—often spectacularly.

Acceptance testing is your only opportunity to verify equipment meets specifications, identify manufacturing defects, and ensure correct installation before energization and warranty expiration.

What is Acceptance Testing?

Acceptance testing is comprehensive commissioning performed on new or extensively refurbished electrical equipment before it enters service. This verification process includes:

Visual & Mechanical Inspection

Verify proper assembly and construction

Electrical Testing

Insulation resistance, dielectric, and functional tests

Protection System Verification

Relay calibration and settings verification

Documentation & Certification

NETA-stamped reports for warranty and compliance

Testing follows ANSI/NETA ATS (Acceptance Testing Specifications) and manufacturer requirements. For mission-critical facilities, NETA-certified testing is the industry standard and often required by specifications, insurance carriers, and warranty terms.

Why This Service is Critical

Defect Detection

Manufacturing defects, shipping damage, and installation errors are common but often invisible during visual inspection. Proper testing identifies these issues before equipment energization.

Real Example:

Data center commissioned new 15kV switchgear without acceptance testing to save time and cost. Six months after energization, a bus fault caused catastrophic failure—loose bus connection created arcing that destroyed three adjacent sections. Investigation found the connection was improperly torqued at the factory. Damage: $1.2M in equipment, 72 hours downtime, customer SLA penalties. Cost of proper acceptance testing: $8,500.

Warranty Protection

Equipment manufacturers require acceptance testing as a condition of warranty. Without NETA-certified test reports documenting proper commissioning, warranty claims may be denied. Acceptance testing must occur before energization—you can't test switchgear insulation after it's been in service.

Code Compliance

NEC Article 110.2 requires installations to meet manufacturer instructions and be suitable for the intended use. Many jurisdictions and authority having jurisdiction (AHJ) require acceptance testing documentation for final inspection approval. Insurance carriers increasingly require testing before issuing coverage.

Safety Verification

Equipment that hasn't been properly tested poses safety risks to operators and maintenance personnel. Insulation failures, incorrect protection settings, and mechanical defects can cause arc flash incidents, electrocution, and explosions. Testing verifies equipment is safe to operate before anyone is exposed to these hazards.

Common Problems This Service Solves

1. Hidden Manufacturing Defects

Quality control at factories isn't perfect. Acceptance testing regularly discovers loose connections, contaminated insulation, incorrectly wired controls, and missing components. These defects cause failures weeks, months, or years after installation—often outside the warranty period.

2. Installation Errors

Even experienced contractors make mistakes. Cable terminations with improper torque, reversed polarity, phase rotation errors, and incorrect protection settings are discovered during acceptance testing. Finding these before energization prevents equipment damage and dangerous operating conditions.

3. Specification Deviations

Equipment delivered may not match specifications. Substituted components, incorrect ratings, and non-compliant materials are common. Without testing, you accept equipment that doesn't meet your requirements. Testing identifies these issues while the manufacturer is still contractually obligated to make corrections.

4. Moisture and Contamination

Equipment exposed to weather during shipment or storage absorbs moisture, drastically reducing insulation strength. Insulation resistance testing identifies contaminated equipment before energization, preventing immediate failures and allowing proper drying procedures.

5. Undocumented As-Built Conditions

Field modifications during installation often aren't documented. Acceptance testing creates a baseline record of equipment conditions, settings, and performance at commissioning—invaluable for future troubleshooting and maintenance planning.

When Should You Schedule This Service?

Required for These Scenarios

  • • All new electrical equipment installations
  • • Major renovations or system expansions
  • • Equipment relocations to new facilities
  • • Extensively refurbished equipment
  • • Equipment after extended storage (6+ months)
  • • Warranty requirement compliance
  • • Insurance or financing conditions
  • • Mission-critical facility commissioning

Timing Considerations

  • After installation completion: All mechanical work finished, terminations complete
  • Before energization: Testing must occur with equipment de-energized
  • Within warranty period: Identify defects while manufacturer is liable
  • Before final payment: Leverage contractor obligation to correct deficiencies

Best Practice: Schedule testing during project planning. Include NETA testing requirements in construction specifications to ensure contractor coordination and budget allocation.

What to Expect During the Service

Phase 1: Pre-Test Planning (1-2 weeks before)

  • • Review equipment specifications and manufacturer data
  • • Develop test plan following ANSI/NETA ATS standards
  • • Coordinate site access and safety procedures
  • • Verify installation completion and readiness

Phase 2: Visual & Mechanical Inspection (Day 1)

  • • Verify equipment ratings match specifications
  • • Inspect for shipping damage and physical defects
  • • Check torque on all electrical connections
  • • Verify proper grounding and bonding
  • • Confirm clearances and installation per code

Phase 3: Electrical Testing (Days 2-4)

  • • Insulation resistance (megohm) testing
  • • Dielectric (high-potential) testing
  • • Contact resistance measurements
  • • Protective relay calibration and functional tests
  • • Circuit breaker timing and travel analysis
  • • Control circuit functionality verification
  • • Phase rotation and voltage verification

Phase 4: Documentation & Closeout (Final day)

  • • NETA-certified test reports with all measurements
  • • Deficiency identification and resolution recommendations
  • • As-tested settings documentation
  • • Equipment baseline records for future maintenance
  • • Warranty activation documentation

Typical Timeline: Simple installations (single piece of equipment) may complete in 1-2 days. Complex projects with multiple interconnected systems can require 1-2 weeks of testing.

ROI & Business Value

Direct Financial Impact

$250K-$2M

Average cost of major equipment failure from undetected defects

$5K-$50K

Typical acceptance testing cost (varies with equipment complexity)

5-400x

ROI from preventing ONE catastrophic failure

Business Benefits

  • • Warranty protection and manufacturer accountability
  • • Insurance coverage compliance
  • • Reduced risk of early equipment failure
  • • Documented baseline for maintenance planning
  • • Code compliance and inspection approval
  • • Confidence in system reliability from day one
  • • Leverage to enforce contractor quality

Hidden Savings:

Testing identifies problems while the contractor is still on-site and contractually obligated to fix them at no cost. After final payment and demobilization, corrections become change orders at premium rates.

Industry Standards & Compliance

ANSI/NETA ATS: Acceptance Testing Specifications

Defines comprehensive testing procedures for new electrical equipment. Industry-recognized standard accepted by manufacturers, engineers, and authorities having jurisdiction.

NEC Article 110.2: Approved Installation

Requires equipment to be installed per manufacturer instructions and be suitable for the intended use. Acceptance testing verifies compliance.

IEEE Standards: Equipment-Specific Testing

IEEE C37 (switchgear), IEEE C57 (transformers), and other standards define specific test methods and acceptance criteria incorporated into NETA procedures.

Manufacturer Requirements

Equipment manufacturers specify commissioning procedures as warranty conditions. NETA testing meets or exceeds these requirements while providing independent third-party verification.

NETA Accreditation: Only NETA-accredited companies can provide NETA-certified test reports. Verify your testing provider is accredited at netaworld.org. Non-accredited testing may not satisfy warranty or specification requirements.

Ensure Your Equipment Investment is Protected

Don't energize new equipment without proper commissioning. The cost of testing is negligible compared to early failure consequences.

What You Get:

  • ✓ Comprehensive NETA-certified testing per ANSI standards
  • ✓ Defect identification before energization
  • ✓ Warranty-compliant documentation
  • ✓ Baseline records for future maintenance
  • ✓ Peace of mind that equipment is safe and ready

📧 support@clarkte.com | ☎️ +1 (617) 396-4632 | 📍 Boston, MA