ClarkTE

Short Circuit Analysis

The Foundation of Electrical System Safety and Protection

When a fault occurs in your electrical system, thousands or even tens of thousands of amperes flow through equipment designed for hundreds of amperes under normal conditions. Can your circuit breakers interrupt these massive currents? Or will they explode trying, endangering workers and destroying equipment?

Without a short circuit analysis, you're operating on hope—not engineering. Short circuit analysis determines whether your equipment can safely handle worst-case fault conditions and forms the basis for arc flash studies, coordination analysis, and equipment selection.

What is Short Circuit Analysis?

Short circuit analysis is an engineering calculation that determines the maximum electrical current that can flow at every point in your power distribution system during fault conditions. The analysis calculates:

Available Fault Current

Maximum short circuit current (in kilo-amperes, or kA) at each bus, panel, switchboard, and equipment location

Equipment Rating Verification

Comparison of calculated fault currents against the Ampere Interrupting Capacity (AIC) of installed devices

Contribution Sources

Identifies all fault current contributors including utility, generators, large motors, and UPS systems

NEC Compliance

Provides required field markings per NEC 110.24 with maximum available fault current and calculation date

For Engineers: Analysis employs symmetrical component theory using ANSI or IEC methods to calculate three-phase and line-to-ground faults. Computer modeling (SKM, ETAP, EasyPower) creates complete impedance network models considering X/R ratios, transformer impedances, conductor properties, and motor contributions.

Why This Service is Critical

Prevent Catastrophic Failures

Every circuit breaker has a maximum fault current it can safely interrupt—its AIC (Ampere Interrupting Capacity) rating. Exceed this rating, and the device can explode violently rather than clearing the fault.

According to IEEE data, 23% of facilities have at least one location where available fault current exceeds installed device ratings. These are "ticking time bombs" waiting for a fault to occur.

Code Compliance

NEC Article 110.9 requires that equipment intended to interrupt current at fault levels shall have an interrupting rating sufficient for the available fault current.

NEC Article 110.24(A) requires service equipment to be field-marked with maximum available fault current, calculation date, and must be updated when modifications occur.

Foundation for All Other Studies

Short circuit analysis is the prerequisite for:

  • Arc Flash Studies (incident energy requires accurate fault currents)
  • Coordination Studies (device selection depends on fault levels)
  • Equipment Selection (new equipment must have adequate ratings)
  • Generator Sizing (understanding system contributions)

Common Problems This Service Solves

Problem #1: Undersized Protective Devices

Scenario: Building constructed in 1985 with 480V service from 500 kVA utility transformer. Breakers rated 18-22 kA AIC—adequate for original system. In 2005, utility upgraded transformer to 1500 kVA. Nobody performed new short circuit study. Available fault current increased from 16 kA to 38 kA.

Result: Every main breaker now faces fault currents exceeding interrupting ratings. A fault could cause breaker explosion, fire, and extensive damage.

Real Cost: Replacing 40 breakers on planned schedule: $65,000
Emergency replacement after catastrophic failure: $400,000+ plus downtime

Problem #2: Unknown Fault Current After System Changes

Healthcare facility added 750 kW emergency generator. Generator sized for load requirements, but nobody analyzed fault current contribution during parallel operation with utility power.

Result: During monthly generator test with utility connected, combined fault contribution exceeded main breaker AIC rating by 8 kA. Facility was one protective device away from major equipment failure.

Problem #3: Missing NEC 110.24 Markings

Facility has no field-marked available fault current labels on service equipment. During insurance audit, carrier notes code violation and requires immediate remedy within 60 days or faces coverage cancellation.

Solution: Short circuit study provides PE-stamped calculations and NEC 110.24 compliant labels.

When Should You Schedule This Service?

Mandatory Timing

  • Immediately if no current study exists
  • Before arc flash or coordination studies
  • After any system changes affecting fault current
  • Every 5 years minimum

Critical Warning Signs

  • No NEC 110.24 fault current markings
  • Utility service or transformer upgrades
  • Generator or UPS installations
  • Insurance audit findings

What to Expect During the Service

1

Data Collection (1-2 weeks)

  • • Electrical single-line diagrams verification
  • • Equipment nameplate data (transformers, breakers, switchboards)
  • • Utility coordination data (available fault current)
  • • Cable routing and conductor sizes
  • • Motor and generator specifications
2

Computer Modeling & Analysis (1-2 weeks)

  • • Complete system model in SKM/ETAP/EasyPower
  • • Three-phase and line-to-ground fault calculations
  • • Peak asymmetrical current calculations
  • • Equipment adequacy verification (calculated vs. rated)
3

Deliverables

  • • PE-stamped technical report (digital + hard copy)
  • • Updated single-line diagrams with fault currents
  • • Equipment adequacy spreadsheet
  • • NEC 110.24 compliance labels
  • • Prioritized recommendations with cost estimates
  • • Electronic model files for future updates

Total Timeline: 4-6 weeks for typical commercial/industrial facility. Expedited service available for urgent compliance needs.

ROI & Business Value

$200K-$750K

Catastrophic breaker failure cost

$6K-$18K

Study investment

11-125x

ROI preventing ONE failure

Informed Capital Planning: Phased replacement budgets vs. emergency spending (60-75% savings)

System Capacity Understanding: Determine if electrical system can support expansions

Faster Future Projects: Having fault current data accelerates arc flash and coordination studies

Industry Standards & Compliance

NEC Requirements

NEC 110.9: Interrupting Rating

Equipment must have interrupting rating sufficient for available fault current

NEC 110.24(A): Fault Current Marking

Service equipment must be field-marked with maximum fault current and date

IEEE Standards

  • IEEE 141 (Red Book): Power Distribution Practice
  • IEEE 551: Short-Circuit Current Calculations
  • IEEE 242 (Buff Book): Protection & Coordination

PE Stamp Required: Calculations must be prepared by or under supervision of licensed Professional Engineer for code compliance, legal defensibility, and insurance acceptance.

Know Your Fault Currents with Engineering Certainty

Under-rated equipment is a hidden danger until the moment of truth arrives—and then it's too late.

What You Get:

  • ✓ Complete short circuit analysis for entire facility
  • ✓ PE-stamped report accepted by all code authorities
  • ✓ Equipment adequacy assessment with recommendations
  • ✓ NEC 110.24 compliant labels
  • ✓ Electronic model for future modifications
  • ✓ Priority-ranked action plan with cost estimates

📧 support@clarkte.com